  Description: The Phase 1 project includes (1) the construction of two test tracks, (2) site work needed to support the facilities, including grading, storm drainage, landscaping and fencing (3) access roads for general traffic and for transporting the Heavy Test Vehicle onto and off the site. Subsequent phases will construct office, storage and testing facilities.

  Project ManagerJulie Sams
  Emailjasams@ucdavis.edu
  Phone530-757-3109
  Design TeamA&E Design Group
  ContractorCollet Construction Co., Inc.
  Size18,950 Gross Sq. Ft.
  11,370 Assignable Sq. Ft.
  Project Budget$15,000,000
  Current PhaseWarranty Phase
  Anticipated OccupancyApril 2009
 
  StatusThe building is finished and occupied
 
  Page Last Updated10/29/2009
 